Primrose Field 16”,18”, 20” Dimple Cladding Insulation
PROJECT DETAILS Strip Cladding, Install Dimple PVC Spacer and Aluminum for Drying Trial
LOCATION CLAWR CNRL Primrose Areas
JOB# 2020-096
START April 19, 2022
COMPLETION November 25, 2022
SIZE OF LINE / LENGTH
NPS 16 Pipeline 226 LM
NPS 18 Pipeline 3050 LM
NPS 20 Pipeline 10,754 LM
MATERIALS
• Outer PVC dimple cladding
• Aluminum Cladding
• Moisture Test Ports (Plugz)
• Shoe box & Clamp covers
• Caulking (Elastomeric)
• Termination gaskets
• IVS Drains & Vents
CLIENT REFERENCE Canadian Natural Resources Limited